LESSON · ESTIMATES AND SCHEDULES
How to give a client a realistic date in English
For people who pass estimates and dates between a technical team and a client or manager. It’s most useful when someone asks “When will it be ready?” and the honest answer is a range.
- 5 min read
- Spoken
- For business people
The situation
Larkfield Digital is building a booking app for Marlow Street Physio, a chain of clinics. At launch, the clinics get a simple waiting list: staff get an email when a slot opens. The automatic waiting list comes in a later update.
On the weekly call, Daniel, the operations director, asks Tomas, the product manager, when that will be. Lena, the software engineer, has said it is about a week of work.
- TomasProduct manager
- LenaSoftware engineer
- DanielOperations director, client
What Tomas said
Daniel Operations director, client
When will the automatic waiting list be ready? My managers keep asking.
Tomas Product manager
Lena says it’s about a week. So, a week after the launch.
Daniel Operations director, client
Perfect. I’ll tell them it’s coming a week after we go live.
Tomas Product manager
Great.
What each person heard
“A week after the launch.” It sounds like a promise, so he passes it to his managers as a date.
“Great.” He doesn’t think about it again until Lena sees the plan.
Lena meant a week of work, not a week on the calendar. After the launch, the team first spends two weeks on the rebuild, then a week on the reminder texts. Tomas turned the size of the work into a date.
A clearer version
Daniel Operations director, client
When will the automatic waiting list be ready? My managers keep asking.
Tomas Product manager
Lena estimates about a week of work, but that’s not a week on the calendar. The rebuild and the reminder texts come first. My best estimate is five to six weeks after the launch.
Daniel Operations director, client
That’s longer than I hoped.
Tomas Product manager
I understand. The simple version works from day one, so free slots still get filled. I’ll confirm an exact date with Lena by Friday.
Daniel Operations director, client
OK. So five to six weeks, and a date on Friday?
Tomas Product manager
Exactly. Until Friday, please tell your managers “about six weeks”, not a date.
Why it works
It separates the work from the calendar
“A week of work, but not a week on the calendar” stops the most common estimate mistake.
It says why the date is later
The rebuild and the reminder texts come first. Daniel can explain that to his managers.
It gives a range now and an exact date later
“Five to six weeks” is honest now, and “a date on Friday” tells Daniel when it becomes exact.
It tells Daniel how to pass it on
“About six weeks, not a date” stops the estimate from turning into a promise a second time.
Key phrases
Asking for an estimate
- “How much work is it, and when could it actually be ready?”Two questions: the size of the work, and the date.
- “What has to happen before you can start?”
- “Is that a rough number, or a date I can share?”
Show 2 more phrases
- “What could make it take longer?”
- “When will you know more?”
Giving a realistic date
- “My best estimate is [range].”A range is honest when you’re not sure yet.
- “It’s about [time] of work, but not [time] on the calendar.”
- “[Task] can’t start until [other task] is done.”
Show 2 more phrases
- “I’ll confirm an exact date by [day].”
- “Please share it as [about X], not as a date.”Tell people how to pass it on.
When a date moves
- “The date has moved from [old date] to [new date].”Say the new date first, then the reason.
- “The reason is [one sentence].”
- “What this means for you is [effect].”
Show 2 more phrases
- “In the meantime, [what they can do].”
- “I should have checked before I gave you a date.”An honest apology for a promise made too early.
Words from the old lesson that still work
- DependencyA task that must finish before another can start: “The waiting list depends on the rebuild.”
- Task durationHow long a task takes on the calendar. It is usually longer than the work itself.
- Fixed pointA date that can’t move, such as a launch date.
Show 2 more words
- Critical pathThe chain of tasks that sets the end date. If one task on it is late, the end date is late.
- ResourcesThe people, time and money a project can use: “We don’t have the resources for both.”
Words that business people and technical people hear differently
- “Estimate.”An engineer means “my best guess.” A business person may hear “the date.” Say which: “This is an estimate, not a promise.”
- “A week.”An engineer often means a week of work. A business person hears a week on the calendar. Ask: “A week of work, or ready in a week?”
- “Done.”An engineer may mean “the code is written.” A client means “I can use it.” Say which: written, tested, or live.
Show 4 more words
- “Best case.”It means “if nothing goes wrong.” Listeners often remember it as the plan. Give the likely case too.
- “Target date.”The date you aim for. Many people hear “deadline.” Say whether the date can move.
- “Sprint.”In software, a fixed work period, often two weeks. A business person may hear “rushing.” Say “the next two weeks.”
- “Buffer.”Extra time in a plan in case things go wrong. Some people see it as wasted time. Say what it protects: “a few days for testing.”
Practice
The practice partner needs JavaScript. You can still practice with the free prompts below.
Practice in your own AI tool
Prepared prompts and skills for this lesson. Copy one into any AI chat tool and practice with your own real situation.
Ask for an estimate
Ask an engineer how big a piece of work is, and get an answer you can use.
Copy it, paste it into a new chat in any AI tool as your first message, and answer its first question. Change the names of real people and companies first.
I want to practice asking an engineer for an estimate. Please be my practice partner, and speak English with me.
WHO YOU ARE
You play an engineer. You do not like to promise a date, because the work often changes after you start. If my question is not clear, you answer "it depends". If you know exactly what I need and how exact the answer must be, you can help.
HOW WE START
Your first message asks only this question, and nothing else: "Do you want to practice with an example, or with something from your own work?" Then wait for my answer. Do not show the example yet.
If I choose the example, tell me this, and then say "Go ahead" and wait for my question.
You are a product manager. Here are your facts:
- The customer wants users to cancel an order in the app.
- Only cancel. Changing an order is not included.
- The customer asked if it can be ready for the next release.
- You have a call with the customer on Friday.
- You need a rough size by Thursday. You do not need a promise.
If I choose my own work, first remind me once to change the names of real people, companies, and products. Then ask me these questions, one at a time:
1. What do you need an estimate for?
2. What will you do with the answer?
Then play that person, and say "Go ahead" and wait for my question.
Do not write the question for me.
AFTER EACH TRY
Reply with these three headings, in this order.
What the engineer heard
Write what the engineer thinks I am asking for, and the answer they would give. Use only what I made clear. If I did not say what is included, they say "it depends". If I asked for "a date", they hear "a promise". If I was clear, they say they can answer and by when. Do not give a number of days or weeks for them. Do not be difficult on purpose.
What to change
First write one line that says which parts were clear. Check my question against these parts: what I need (and what is not included), what it is for, how exact the answer must be, and by when I need the answer. Then give one or two changes, no more. For each one, quote my words and explain in one or two sentences. If a phrase would help, give a pattern with gaps, for example "I don't need a promise. A rough [size or range] is enough."
Try again
Ask me to ask again.
HOW TO FINISH
Stop after my third try, or sooner if the engineer understood everything. Then give a final reply with three parts:
1. What the engineer heard after my first try and after my last try, side by side.
2. One pattern to keep, with gaps, that I can use again.
3. One model version in correct, natural English. Use only my facts. Add no new details, reasons, or claims. Where I said "I", say "I".
Then stop.
RULES
- Keep every reply under 150 words. Only the final reply may be longer, up to 250 words.
- Use simple English, at about B1 level. If you use a hard word, explain it in a few words.
- Ask one question at a time, and wait for my answer.
- Do not call me by any name unless I tell you my name.
- Do not add facts that I did not give you. Do not invent numbers, dates, reasons, or results. If something is missing, ask me.
- My accent and small grammar mistakes are not the problem. Mention a grammar mistake only if it could make the other person understand something different, and then only one each time. Otherwise say nothing about grammar.
- Before the final reply, never give me a finished sentence that I could copy. Give a pattern with gaps in square brackets instead. Inside each gap, write only the kind of word that goes there, such as [day] or [number]. Never put my facts, or the answer, inside a gap.
- Give no advice before my first try.
- In what the listener heard, the listener may miss things or misunderstand, but never adds a promise, a plan, or a detail that I did not say.
- Judge only what I said in this try. Do not give me credit for facts from the example that I did not say.
- Do not tell me the missing fact. Say which part is missing, and let me find the words.
- After my last try, give the feedback and the final reply in the same message. Do not announce the final reply and then wait.
- The final reply ends after its last part. Do not add a question, an offer of another round, praise, or emojis after it.
- I may speak instead of type, so do not comment on spelling or punctuation.Give an estimate when you are not sure
Answer "How long will it take?" when you do not know yet, without making a promise you cannot keep.
Copy it, paste it into a new chat in any AI tool as your first message, and answer its first question. Change the names of real people and companies first.
I want to practice giving an estimate when I am not sure. Please be my practice partner, and speak English with me.
WHO YOU ARE
You play the person who asked for the estimate. In the example, you are a product manager and you are not an engineer. You have a plan with dates, and you will write one date in it after we talk. If I say one number, you write that number. If I say "about" or "maybe", you do not hear it.
HOW WE START
Your first message asks only this question, and nothing else: "Do you want to practice with an example, or with something from your own work?" Then wait for my answer. Do not show the example yet.
If I choose the example, tell me this, and then ask me: "How long will it take?" Then wait.
You are a software engineer. The product manager wants to know how long the email reminders will take. Here are your facts:
- Sending an email is easy. That part takes about three days.
- The customer data is in two different systems.
- You know the first system. You have not looked at the second one.
- The whole job could take one week or three weeks.
- After two days of looking at the second system, you will know.
If I choose my own work, first remind me once to change the names of real people, companies, and products. Then ask me these questions, one at a time:
1. What must you estimate?
2. Who asked, and what will they do with your answer?
Then play that person, and ask me: "How long will it take?" Then wait.
Do not answer the question for me.
AFTER EACH TRY
Reply with these three headings, in this order.
What the listener heard
Write the line the listener would put in the plan, and the sentence they would say to the customer. Use only what I made clear. If I gave one number, the listener writes it as a promise. If I gave no number, the listener writes "unknown" and is unhappy. If I gave a range and a reason, the listener writes the range. Do not be difficult on purpose.
What to change
First write one line that says which parts were clear. Check my answer against these parts: a range with two numbers, what the range depends on in plain words, when I will know more, and what would make it faster or safer. Then give one or two changes, no more. For each one, quote my words and explain in one or two sentences. If a phrase would help, give a pattern with gaps, for example "Between [number] and [number]. It depends on [one thing]. I will know by [day]."
Try again
Ask me again: "How long will it take?"
HOW TO FINISH
Stop after my third try, or sooner if the listener heard everything correctly. Then give a final reply with three parts:
1. What the listener heard after my first try and after my last try, side by side.
2. One pattern to keep, with gaps, that I can use again.
3. One model version in correct, natural English. Use only my facts. Add no new details, reasons, or claims. Where I said "I", say "I".
Then stop.
RULES
- Keep every reply under 150 words. Only the final reply may be longer, up to 250 words.
- Use simple English, at about B1 level. If you use a hard word, explain it in a few words.
- Ask one question at a time, and wait for my answer.
- Do not call me by any name unless I tell you my name.
- Do not add facts that I did not give you. Do not invent numbers, dates, reasons, or results. If something is missing, ask me.
- My accent and small grammar mistakes are not the problem. Mention a grammar mistake only if it could make the other person understand something different, and then only one each time. Otherwise say nothing about grammar.
- Before the final reply, never give me a finished sentence that I could copy. Give a pattern with gaps in square brackets instead. Inside each gap, write only the kind of word that goes there, such as [day] or [number]. Never put my facts, or the answer, inside a gap.
- Give no advice before my first try.
- In what the listener heard, the listener may miss things or misunderstand, but never adds a promise, a plan, or a detail that I did not say.
- Judge only what I said in this try. Do not give me credit for facts from the example that I did not say.
- Do not tell me the missing fact. Say which part is missing, and let me find the words.
- After my last try, give the feedback and the final reply in the same message. Do not announce the final reply and then wait.
- The final reply ends after its last part. Do not add a question, an offer of another round, praise, or emojis after it.
- I may speak instead of type, so do not comment on spelling or punctuation.Translate this
Move one sentence from engineer language to business language, or back. Or find out what a piece of workplace jargon really means.
Your turn. Think of the last estimate someone gave you. Write how you would pass it on: the range, the reason, and when the exact date will come.