LESSON · ESTIMATES AND SCHEDULES

How to say when it will be done in English

For people who build the work and get asked “When will it be done?” in a chat. It’s most useful when the honest answer depends on something that isn’t finished yet.

  • 5 min read
  • Written
  • For technical people
Live AI practice · free
01

The situation

Larkfield Digital is building a booking app for Marlow Street Physio, a chain of clinics. Lena, the software engineer, is finishing the screen where patients cancel appointments. Next she builds the simple waiting list, about two days of work.

On Monday, Tomas, the product manager, asks in the team chat when the waiting list will be done. Every Friday he sends Grace, the director, an update.

  • TomasProduct manager
  • LenaSoftware engineer
  • GraceDirector
02

What Lena wrote

First version
#clinic-app

Tomas Product manager

Lena, when will the simple waiting list be done? Grace always asks in my Friday update.

Lena Software engineer

The simple waiting list starts from a cancellation, so it needs the cancellation screen first. I’m still on that, testing each way a patient can cancel. Then the list itself is about two days.

Tomas Product manager

Great, thanks!

03

What each person heard

Tomas heard

“This week.” “About two days” is the only number in the message, so it sounds like Wednesday or Thursday. “Still on that” sounds like nearly done, not like a warning. On Friday he writes to Grace: “Simple waiting list: ready this week.”

Lena meant

“I can’t start yet, and I don’t know when the cancellation screen will be finished.”

Lena’s facts were right, and in the order the work happens. But the only number was the size of the work, not a day, and the one thing that could move it was hidden in the middle.

04

A clearer version

Clearer version
#clinic-app

Tomas Product manager

Lena, when will the simple waiting list be done? Grace always asks in my Friday update.

Lena Software engineer

It’s about two days of work, and I start it when the cancellation screen is finished. If that’s done by Tuesday, the waiting list will be ready on Thursday. If the cancellation screen needs more fixes, it moves to Monday. I’ll know for sure on Tuesday afternoon, and I’ll tell you here.

Tomas Product manager

Perfect. So: Thursday, or Monday at the latest. I’ll wait for your Tuesday message before I tell Grace anything.

Lena Software engineer

Thanks. I’ll write by the end of Tuesday.

05

Why it works

1

It gives a day, not a feeling

“The waiting list will be ready on Thursday” is something Tomas can write down. “About two days” is the size of the work, not a day.

2

It names the one thing that could move it

“If the cancellation screen needs more fixes” tells Tomas what to watch.

3

It gives the other day too

“It moves to Monday” means the worst case is clear, so nobody is surprised.

4

It says when the answer will be sure

“I’ll know for sure on Tuesday afternoon” gives Tomas a reason to wait before he writes to Grace.

06

Key phrases

Giving a day

  • “It’s about [amount] of work.”Start with the size, so the reader understands the day that follows.
  • “If [condition], it will be ready on [day].”The condition comes first, so nobody reads the day as a promise.
  • “[Day], or [day] at the latest.”The person passing it on can use these words exactly.
Show 2 more phrases
  • “I can start it when [task] is finished.”Use this when the work is waiting for something else.
  • “My best guess is [day], but it isn’t certain yet.”

Saying what could move it

  • “If [problem], it moves to [day].”Give the later day, not only the risk.
  • “The one thing that could move it is [thing].”
  • “It depends on [thing]. I’ll know more by [day].”
Show 2 more phrases
  • “Nothing else is blocking it.”
  • “If [thing] happens, I’ll tell you the same day.”A risk with a promise attached is easier to hear.

Saying when you’ll know

  • “I’ll know for sure on [day].”
  • “I’ll tell you here by [time or day].”Then do it, even if the answer is “no change”.
  • “Can you wait until [day] before you tell [name]?”Useful when someone will pass your answer on.
Show 2 more phrases
  • “I’ll confirm the day by [day].”Pick a day before the other person has to report.
  • “If it changes, you’ll hear it from me first.”It tells the reader they won’t be surprised by someone else.

Words that business people and technical people read differently

  • “Soon.”The writer means “I don’t know yet.” The reader hears “in a day or two.” Give a day, or say when you’ll have one.
  • “Hopefully.”The writer means “this might not happen.” The reader often sees a polite word and skips it. Say the risk in its own sentence.
  • “Done.”An engineer may mean “the code is written.” A manager may hear “the clinics can use it.” Say what done means: “ready in the test version.”
Show 4 more words
  • “This week.”One person means by Friday. Another means “starting this week.” Name the day.
  • “End of day.”It can mean 5 p.m., midnight, or “before I go home.” Say the time, or “by the end of Tuesday.”
  • “Should be fine.”The writer means “probably.” The reader hears “yes.” If there’s a condition, write it.
  • “ETA.”Team English for “the time it will arrive or be ready.” Not every reader knows it. Write “ready on [day].”
07

Practice

The practice partner needs JavaScript. You can still practice with the free prompts below.

Practice in your own AI tool

Prepared prompts and skills for this lesson. Copy one into any AI chat tool and practice with your own real situation.

PromptDraft

Give an estimate when you are not sure

Answer "How long will it take?" when you do not know yet, without making a promise you cannot keep.

  • The AI plays a product manager who will write one date in a plan
  • About 10 minutes · Spoken
SkillDraft

Said, heard, say it again

Practice any short message at work with a listener who tells you what they understood. Then say it again.

  • Use it for stand-up updates, delays, estimates, requests, saying no, disagreeing, and explaining something technical. One skill covers all of them, because it asks about your situation first.

Your turn. Think of the last time someone asked you when your work would be done. Write the answer again: a day, what could move it, and when you would know for sure.